                            TABLE OF CONTENTS
PURPOSE AND OBJECTIVE(S)
BACKGROUND
SCOPE
REFERENCES
RESPONSABILITIES
	Validation Specialist
	Quality Dept.
	Facility Dept.
METHODOLOGY
	Verification Data Sheet
	Deviation Report
	Signature Log Sheet
	Test Instruments Calibration
EQUIPMENT/PROCESS DESCRIPTION
	Water Softener
	Ozone Generator
	Reverse Osmosis
	Mixed Bed
	Ozone Destructor
	De-gasifier
	UV lights
	Filters
	Distribution Pumps
	Tanks
 6, 000 and 8, 000 Gal. Tanks
 30 um filters (2)
 Distribution Pumps (4)
 1 um filters (4)
 Dual Reverse Osmosis unit
 0.2 um filters (4)
 Dual Mix Bed unit
 Dual Softener unit
 UV lamps (4)
 Ozone Generator
 Degasification unit
 Ozone Destructor
 Microza filters (18)
APPENDIX I: DEVIATION REPORT
APPENDIX II: SIGNATURE IDENTIFICATION LOG SHEET
APPENDIX III: TESTING INSTRUMENTS LOG SHEET
IQ CHECKLIST VERIFICATION
                        
Document Text Contents
Page 1

INSTALLATION QUALIFICATION PROTOCOL


For the


NEW PURIFIED WATER SYSTEM


Prepared by



____________________________________

Page 2

TABLE OF CONTENTS
1.0 PURPOSE AND OBJECTIVE(S) .................................................................................................................................... 4

2.0 BACKGROUND .............................................................................................................................................................. 4

3.0 SCOPE ........................................................................................................................................................................... 4

4.0 REFERENCES ............................................................................................................................................................... 4

5.0 RESPONSABILITIES ...................................................................................................................................................... 5

5.1 Validation Specialist ................................................................................................................................................... 5

5.2 Quality Dept. ............................................................................................................................................................... 5

5.3 Facility Dept. ............................................................................................................................................................... 5

6.0 METHODOLOGY ............................................................................................................................................................ 6

6.1 Verification Data Sheet ............................................................................................................................................... 6

6.2 Deviation Report ......................................................................................................................................................... 6

6.3 Signature Log Sheet ................................................................................................................................................... 6

6.4 Test Instruments Calibration ....................................................................................................................................... 6

7.0 EQUIPMENT/PROCESS DESCRIPTION ....................................................................................................................... 7

7.1 Water Softener ........................................................................................................................................................... 7

7.2 Ozone Generator ........................................................................................................................................................ 7

7.3 Reverse Osmosis ....................................................................................................................................................... 7

7.4 Mixed Bed................................................................................................................................................................... 7

7.5 Ozone Destructor ....................................................................................................................................................... 7

7.6 De-gasifier .................................................................................................................................................................. 8

7.7 UV light ....................................................................................................................................................................... 8

7.8 Filter ........................................................................................................................................................................... 8

APPENDIX I: DEVIATION REPORT .......................................................................................................................................... 11

APPENDIX II: SIGNATURE IDENTIFICATION LOG SHEET .................................................................................................... 12

APPENDIX III: TESTING INSTRUMENTS LOG SHEET ........................................................................................................... 13

IQ-01 EQUIPMENT VERIFICATION .......................................................................................................................................... 15

IQ-02 DOCUMENT INVENTORY VERIFICATION .................................................................................................................... 37

IQ-03 DRAWING VERIFICATION .............................................................................................................................................. 56

IQ-04 SYSTEM DESIGN VERIFICATION .................................................................................................................................. 58

IQ-05 PLACEMENT VERIFICATION ......................................................................................................................................... 60

IQ-06 UTILITY VERIFICATION .................................................................................................................................................. 67

IQ-07 INSTRUMENTATION VERIFICATION ............................................................................................................................. 86

IQ-08 MAINTENANCE VERIFICATION ..................................................................................................................................... 88

IQ-09 SAFETY & ERGONOMICS VERIFICATION .................................................................................................................. 107

IQ-10 PROCEDURE VERIFICATION ...................................................................................................................................... 109

IQ CHECKLIST VERIFICATION .............................................................................................................................................. 127

Page 63

PLACEMENT VERIFICATION IQ-05


SKID #3 - Distribution Pumps 1A, 1B ; UV lamps 1A, 1B & Filter set 3A, 3B


SPEC EXPECTED RESULT ACTUAL RESULT PASS/FAIL
PERFORMED

BY/DATE

Position
The equipment shall

be located along open
type waste drains.



Environment
The equipment is not

placed on direct
sunlight or other
sources of heat.



Comments/Observations:

Conformance to the acceptance criteria was evaluated and the final determination is as follows:
Acceptance Criteria met? (YES/NO) __________ If NO, refer to Deviation # __________

Reviewed by: Date:

Page 64

PLACEMENT VERIFICATION IQ-05


SKID #4 - R. O. Piping/Valves


SPEC EXPECTED RESULT ACTUAL RESULT PASS/FAIL
PERFORMED

BY/DATE

Position
The equipment shall

be located along open
type waste drains.



Environment
The equipment is not

placed on direct
sunlight or other
sources of heat.



Comments/Observations:

Conformance to the acceptance criteria was evaluated and the final determination is as follows:
Acceptance Criteria met? (YES/NO) __________ If NO, refer to Deviation # __________

Reviewed by: Date:

Page 126

PROCEDURE VERIFICATION IQ-10


Microza “ultra filtration” filters


SOP
EXPECTED

RESULT
ACTUAL RESULT

(DOC. NO., REV. NO., TITLE, STATUS)
PASS/FAIL

PERFORMED
BY/DATE

Operating
Procedure

A procedure
exists at least in

Draft form.


Maintenance
Procedure

A procedure
exists at least in

Draft form.


Comments/Observations:

Conformance to the acceptance criteria was evaluated and the final determination is as follows:
Acceptance Criteria met? (YES/NO) __________ If NO, refer to Deviation # __________

Reviewed by: Date:

Page 127

IQ CHECKLIST VERIFICATION


Verify each of the respective IQ tests and document completion and status.


TEST
NUMBER TEST TITLE

TEST
EXECUTED
(YES/NO)

ACCEPTANCE
CRITERIA

MET?
(YES/NO)

DEVIATION
NUMBER

(if applies)

DEVIATION
SOLVED

(YES/NO)

IQ-01 EQUIPMENT VERIFICATION

IQ-02 DOCUMENT INVENTORY VERIFICATION

IQ-03 DRAWING VERIFICATION

IQ-04 SYSTEM DESIGN VERIFICATION

IQ-05 PLACEMENT VERIFICATION

IQ-06 UTILITY VERIFICATION

IQ-07 INSTRUMENTATION VERIFICATION

IQ-08 MAINTENANCE VERIFICATION

IQ-09 SAFETY AND ERGONOMICS VERIFICATION

IQ-10 PROCEDURE VERIFICATION

Performed by: Date: